Cory Cogen Power Station
GT Inlet Filtration Unit Replacement
Project Description
This project involved the demolition and replacement of two air filtration systems at SaskPower’s gas-fired power station in Saskatoon. The scope included structural, mechanical, electrical, and piping work, with commissioning support provided to ensure seamless integration of the new systems.
Scope of Work Included:
1] Demolition: Removal of two existing air filtration systems
2] Installation:
– New filtration units including filter modules, service modules, rain hoods, and clean air plenums
– Support steel, platforms, stairs, and ladders
– Electrical systems for control and instrumentation
– Associated piping systems
Trades and Sub-Trades Involved:
– Trades/techs: General foreman, iron workers, electricians, pipefitters
– Sub-trades: Coatings, crane services, insulation
Market Scope
This project served the power generation market, supporting SaskPower’s infrastructure upgrades for cleaner and more efficient energy production. The installation of modern air filtration systems enhances operational reliability and environmental compliance at the Saskatoon facility.
Date of Completion
May 18, 2026
Client
SaskPower
Location
Saskatoon, SK
Facility Classification
Gas-fired power station
Markets Served
Power generation